October 15, 2026
The playground at Beeman Park closed in September so crews could work near its access ramp. By the Studio City Neighborhood Council's October 7 update, it was open again, which the council called "good news." The building rising behind the construction fence on Rye Street is a different story. Its design was finished and permitted in 2018. Construction didn't start for another six years, and the problems that kept it unbuilt are still showing up as change orders on the job site today.
That gap between paper and pavement explains the timing of the Studio City Recreation Center rebuild, the cost, and why three official sources give three different finish dates.
The Studio City Recreation Center is an 8.46-acre park at 12621 West Rye Street, and most of it has stayed open through construction. The indoor recreation center closed on September 9, 2024. The city's facility page says the outdoor amenities would stay open.
As of the October 7 update, here is where things stand:
The diamond carries more traffic than most park fields. A Recreation and Parks board report from October 1, 2026, describes the park's youth baseball program as "the second largest program offered in public parks." That is a lot of weeknight and weekend use for a park whose main building is a construction site.
The old community building was 5,723 square feet. Council District 4 dates the gym inside it to 1952. The plan to replace it began as a city experiment. According to the October 2026 board report, "The Project was initially designed over 10 years ago as a sustainable design pilot project for gymnasiums in the City of Los Angeles."
Here is how the timeline played out:
| Date | What happened |
|---|---|
| 2018 | Design completed and permitted |
| November 2019 | City report shows the budget rising from $10.686 million to $16.005 million, with an $8.55 million funding gap |
| March 2020 | Two construction bids received |
| July 2020 | Both bids rejected as nonresponsive |
| 2021 | Project restarted after the city sought grant funding |
| January 2024 | Board authorizes rebidding |
| July 18, 2024 | Contract awarded to Ford E.C., Inc. for $22,225,000 |
| August 2024 | Groundbreaking with Councilmember Nithya Raman |
| September 9, 2024 | Recreation center closes to the public |
| October 2026 | Construction 79% complete |
Count the years. About six passed between permit and contract. If the March 2027 forecast holds, construction will have taken about 32 months. Most of the wait for this gym happened before anyone dug.
Money closed the gap. A 2019 city report said construction could start in mid-2020 only if full funding was in place, and it wasn't. The funding that eventually came together mixes Proposition K "L.A. for Kids" money, Quimby fees, MICLA financing, and a $3 million federal HUD grant. Council District 4's groundbreaking release credits Congressman Brad Sherman with securing that final $3 million and former councilmember Paul Krekorian with earlier advocacy. The project started on the city's books as a Council District 2 Prop K project. Beeman Park is now in Council District 4.
A permitted design is meant to be ready to build. Between the 2018 permit and the 2024 contract, this one lost both its authors and its code basis, and the October board report describes how each loss turned into change orders.
The design team went first. The report says, "Key staff that led the design for all the design disciplines left the City as part of the early retirement plan offered during the COVID-19 Pandemic." The staff who took over updated the plans to the 2020 Building Code. According to the report, they did not do the extra quality checks needed to make sure the building's newer sustainable systems were coordinated across every trade. The report notes those systems use technology Recreation and Parks had not used on earlier projects.
The code basis shifted next. By the time crews were working, the 2023 Building Code applied, and the report says some conflicts with the 2020 version "were exposed and addressed as Change Orders."
There were also problems on the site that no drawing could have shown. The report lists delays from the Department of Water and Power in updating the transformer yard and power duct bank design, undocumented infrastructure found underground, new utility requirements, and structural changes made during construction.
Here is what that adds up to as of October 1, 2026:
The report says time-impact claims make up most of those forecast costs. In other words, a large share of the remaining bill is the cost of the schedule moving. If the board approves the report, the project's funding would total $26.425 million, $22.225 million for construction plus the $4.2 million contingency. That is about two and a half times the $10.686 million figure the 2019 report started from.
Ask when the gym opens and you'll hear "early 2027." That holds up, but the official sources put it in three different ways, and they're tracking different milestones.
Of the three, the board report is the only one that explains the time-impact change orders behind its forecast. Substantial completion usually comes before a ribbon-cutting. A spring 2027 opening fits all three sources better than a January one.
The new building is 12,000 square feet, a little over twice the size of the building it replaces. Plans call for a full-size basketball court, multipurpose rooms, a recreation center office, a kitchen, restrooms, and support space. Recreation and Parks says the extra room is for its programs and classes.
The sustainability features that started this as a pilot are still in the plan. A 4,000-square-foot rooftop solar array was bid as an add-on and included in the contract award. The project is aiming for both LEED certification and the Living Future Institute's Net Zero certification. The Neighborhood Council describes the result as a 100% solar-powered, net-zero energy building.
Outside the building, the work includes new hardscape for walking and gathering, turf and irrigation repairs, new trees and shade, and a larger parking lot. The Neighborhood Council also lists upgraded picnic areas, walkways, and water fountains. Neither source gives a space count for the expanded lot or a date for reopening the Landale Street entrance. The fence went out to make room for this final phase, so that entrance will likely be among the last pieces to come back.
For now, the playground is open, the ball field and courts are in use, and the building is 79% done. The October 7 update said the play area is set up to stay open until the gym is finished.
At Tammy Jerome, we follow projects like the Beeman Park rebuild because they shape daily life on the blocks around them. If you live near Rye Street and have questions about what the finished park means for your corner of Studio City, Let's Connect.
November 5, 2026
October 29, 2026
Home Selling
October 27, 2026
The FOMO buyer is gone. Today's California buyer brings a spreadsheet, a checklist, and time, and that changes everything for sellers.
October 22, 2026
Home Selling
October 15, 2026
From clearing gutters to testing detectors and packing an emergency kit, these simple fall tasks help your home weather a stormy winter.
October 15, 2026
October 13, 2026
Hoping the market sorts itself out usually means fewer showings and lower offers. Here's what a real listing plan does instead.
October 8, 2026
October 1, 2026
Get assistance in determining current property value, crafting a competitive offer, writing and negotiating a contract, and much more. Contact me today.